UL 1017/CSA C22.2 No.243:25 Important changes to the new standard
Time:
2025-04-24
UL 1017/CSA C22.2 No. 243: The new version of the 25 standard has been released, which applies to products such as vacuum cleaners, blowers, and home floor processors.

The important changes in the new standard are summarized as follows:
|
Standard chapter number |
Explanation of Differences in Standard Requirements | Notes |
|
1.2 |
Added relevant requirements for ash vacuum cleaners. |
New requirement |
|
4.2.1.8 |
Accept the use of hot wire testing, GWFI and GWIT values as alternatives to the HB flame retardant rating requirements. |
Modified requirement |
|
4.2.6 |
Button batteries with a diameter ≤ 32mm in household products require an additional UL 4200A assessment. |
Modified requirement |
|
Table 4.2 |
Charging base stations evaluated using this standard are allowed to use SPT-2 power cords. |
Modified requirement |
|
4.5.1.8 |
The rated current requirement for the plug has been changed from ≥ 1.25 times the rated current of the entire machine to ≥ the rated current of the entire machine. |
Modified requirement |
|
4.5.1.16 |
The minimum length of the power cord for the charging base station evaluated using this standard is changed to 0.9m. |
Modified requirement |
|
4.7.5.8 |
Added requirements for terminals injection molded from elastic materials. | New requirement |
|
4.8.2 |
Add PTI as an alternative solution for CTI. |
Modified requirement |
|
5.2.1.3 |
Clarify the testing method for temperature rise of dust collection piles: work for three cycles, with a 2-minute interval between two cycles. | New requirement |
|
5.2.1.4 |
The pressure relief valve evaluated through durability testing in Chapter 5.30 is allowed to operate during input and normal temperature rise testing. |
Modified requirement |
|
5.2.2.4 |
For products with protective functions that prevent accurate measurement of fully closed power, the average power can be calculated by air flow rate. | New requirement |
|
5.2.2.7 5.2.6.2.1 5.2.4.3 |
For products specifically designed for flooring, pre polished brick surfaces can be used as the testing surface instead of carpets during temperature rise testing. |
Modified requirement |
|
5.12.8.2.1 |
In floor/carpet cleaning machines, for water tanks that need to be taken out separately for water filling or drainage, a separate drop test needs to be conducted with the water tank filled. |
Modified requirement |
|
5.21.7 |
Clearly, brushless motors do not require this test. |
Modified requirement |
|
5.21.7 |
Clarify the requirements for protective devices that operate during the whole machine stall test. |
Modified requirement |
|
6.17.1.1 |
Cancel the motor overload test for air load motors for double insulated products. | Modified requirement |
|
7.1.2 |
Update warning statements about charging vacuum cleaners. |
Modified requirement |
|
7.2.3 |
Regarding the robotic vacuum cleaner, relevant sentence requirements have been added to the instruction manual. |
Modified requirement |
|
7.2.7 |
Added an assessment of the risk of accidental water absorption or exposure to water during the use of robotic vacuum cleaners. | New requirement |
|
7.2.13 |
Added evaluation on fall protection for robotic vacuum cleaners. |
New requirement |
|
7.2.13 |
Added evaluation on the collision energy of robotic vacuum cleaners. | New requirement |
|
9.7.1 |
Products that generate lasers need to comply with the Code of Federal Regulations, CFR 21, Part 1040, Chapter 1, Subchapter J in addition to Consolidated Regulations of Canada, CRC C.1370. | New requirement |
|
9.7.2 |
Products with light sources for illumination must comply with 6.3 of UL 62841-1/CSA C22.2 No. 62841-1 | New requirement |
|
12.1.6 |
The instructions that specify the standard requirements must be provided in the form of printed materials. If an electronic version of the manual is provided, it must also include all statements required by the standard. | New requirement |
|
F.1 |
Updated and optimized the evaluation flowchart for PFHC. |
Modified requirement |
The mandatory implementation date for the new version of the standard has not been determined yet. We will continue to follow up on the relevant situation and release it in a timely manner. Please stay tuned!